Overview
New Albany covers the New Albany International Business Park and the farmland around it. The market runs from Franklin County east into Johnstown, Jersey Township and Pataskala in Licking County. It sits northeast of downtown Columbus along State Route 161. Meta, Google, Amazon and Microsoft own land here, alongside QTS, Vantage, EdgeConneX, Cologix, CyrusOne and STACK. Most of the growth came after 2017, and much of it is still under construction.
History
The New Albany Company developed the business park as a corporate campus for office and industrial tenants. The City of New Albany built a redundant fiber network across the park. AEP placed a mission-critical facility there in 2008. Enterprise data centers followed. Nationwide began building a data center on Souder Road in 2010. TJX moved its data center from Massachusetts in 2013, and Discover opened one the same year. Compass Datacenters built a dedicated facility for AEP in 2015. STACK Infrastructure bought the Nationwide building in 2019.
Hyperscale demand arrived next. In 2015 Amazon chose New Albany as one of three campuses for its AWS US East (Ohio) cloud region, which opened in October 2016. Facebook announced its first Ohio data center here in August 2017. Its first two buildings went live in February 2020. Google bought land on Beech Road in late 2018 and began building in 2019.
Intel's January 2022 decision to build a chip plant in Licking County pulled the market east. Developers assembled farmland around Johnstown and Jersey Township. QTS announced four buildings on Beech Road in 2023. Vantage broke ground on Horizon Court in 2024. Cologix bought land for an eight-building campus in Johnstown the same year. CyrusOne broke ground in 2025, and EdgeConneX began converting a warehouse into its first building.
The Market Today
Meta anchors the market. Its original five-building campus on Beech Road now forms the core of Prometheus, a large AI training cluster. Prometheus adds purpose-built halls and tent-style structures to the south and north of the original campus. Google runs seven buildings on its campus and is building another on Harrison Road. Amazon operates several campuses in the park. Microsoft has finished site work on Beech Road for future phases.
Wholesale supply has grown fast. QTS has two campuses on Beech Road and holds land for two more. Vantage, EdgeConneX, CyrusOne and Cologix are building hyperscale-ready campuses east of Beech Road and around Johnstown. STACK, Edged and CENTRA serve smaller deployments near the original park core.
Enterprise data centers for Discover, TJX and AEP still operate in the original business park. Karis Critical holds an entitled campus site north of State Route 161. Aligned owns land in Pataskala, where its plans now face a local ban.
Advantages
-
Entitled land. The business park offers parcels zoned for data centers, with roads, water and sewer in place.
-
Tax incentives. Ohio exempts qualifying data center equipment from sales tax. New Albany and Johnstown add property-tax abatements of up to 100% for 15 years.
-
Transmission. AEP Ohio has built a ring of new 138 kV and 345 kV substations across the park to serve individual campuses.
-
Network. The city runs a redundant fiber network through the park, and the AWS cloud region sits in the same corridor.
-
A second utility. The Energy Cooperative serves parts of Licking County, which gives some sites an alternative to AEP Ohio.
Challenges
-
Grid access. AEP Ohio paused new data center service commitments in central Ohio in 2023. Since July 2025, new loads over 25 MW pay for at least 85% of contracted demand for up to 12 years.
-
Rezoning freeze. New Albany stopped approving new data center rezonings in April 2025. New projects must use land already zoned or move to neighboring towns.
-
Local bans. Pataskala voters banned data centers of 25 MW or more in November 2026. Johnstown votes on a similar ban in January 2027.
-
Land cost. Recent data center land sales in the corridor cleared $300,000 per acre.
-
Gas-plant opposition. Residents have packed hearings on the on-site gas plants that power several campuses, citing air pollution.
-
State incentives. Ohio paused new data center sales-tax exemption agreements in May 2026. Existing agreements continue.
Trends
-
Bring-your-own power. Williams builds natural gas plants dedicated to Meta, and an EdgeConneX affiliate builds plants for its own campuses. Seven on-site gas plants totaling about 1.9 GW are online, under construction or in permitting.
-
Faster AI builds. Meta deploys tent-style halls beside purpose-built buildings to bring compute online sooner.
-
Fuel cells. AEP Ohio owns and runs fuel cells at a Johnstown campus under a 15-year contract approved in 2025.
-
Eastward expansion. New campuses spread east into Johnstown, Jersey Township and Monroe Township, around the Intel site. Intel now expects its first fab to start production in 2030 or 2031.
-
Local pushback. Ballot bans spread across Licking County in 2026, and more votes are scheduled.
Power and Policy
PJM Interconnection runs the grid and the wholesale power market, and AEP Ohio is the main utility in the park. The Energy Cooperative, a rural electric cooperative, holds the service territory for much of the Licking County side. The Public Utilities Commission of Ohio (PUCO) sets retail rates and approved AEP Ohio's data center tariff in July 2025. The Ohio Power Siting Board (OPSB) approves the substations, transmission lines and on-site gas plants that serve each campus. AEP Ohio expects New Albany-area load to grow from about 500 MW today to more than 2,000 MW by the end of 2027.