Overview
Waco (Central Texas) spans the counties between Dallas-Fort Worth, Austin and Houston, from Hill and Bosque counties south to the Brazos Valley around Bryan. Interstate 35 and Interstate 45 cross it on their way between those metros. Its colocation market is small and sits in downtown Waco and downtown Bryan. Since 2025 the region has become one of the busiest AI campus markets in Texas. Developers build beside its gas and coal plants, or bring their own gas generation.
History
Telephone companies built the region's first data facilities. Southwestern Bell, GTE and United Telephone opened central offices across the region from the 1930s on. AT&T, Verizon and Brightspeed still run many of them. FiberTown opened its Bryan data center downtown in 2007. In 2009 Clearview International opened the Information Technology Gateway in a hardened former fallout shelter in downtown Waco. Zayo bought Clearview in April 2016. DataBank bought zColo's US data centers, including Waco, in December 2020. In February 2023 the infrastructure fund Aphorio Carter bought FiberTown's Bryan property, and FiberTown stayed on under a net lease.
Power plants shaped the region long before data centers arrived. For decades, lignite mines fed large coal plants in Freestone, Limestone and Grimes counties. Two of them closed in 2018: Big Brown near Fairfield and Gibbons Creek in Grimes County. The Sandy Creek plant near Riesel opened in 2013 as the newest large coal plant in the US. Winter Storm Uri hit the grid in February 2021. It left Waco-based Brazos Electric Power Cooperative owing about $1.9 billion to the Electric Reliability Council of Texas (ERCOT). The cooperative filed for bankruptcy on March 1, 2021.
The AI wave reached the region in 2025. In July 2025 Calpine and CyrusOne announced a powered-land campus beside Calpine's Thad Hill Energy Center in Bosque County. The two companies expanded the deal that November. In February 2026 CyrusOne signed a second deal with Calpine, by then part of Constellation, at the Freestone Energy Center near Fairfield. It broke ground there in June 2026.
The Market Today
DataBank's Waco ACT1 serves enterprise colocation customers downtown, and Lumen runs a long-haul fiber node with a small colocation room. In the Bryan area, FiberTown hosts a point of the FD-IX Houston internet exchange, and Crosspoint Data offers colocation and disaster recovery space. Texas A&M University runs its own West Campus Data Center. Duos Edge AI opened a modular edge data center for area schools in Waco in 2026.
The wholesale pipeline sits in the countryside along I-35 and I-45. CyrusOne is building five buildings on its Bosque County campus near Lake Whitney, and state records list Google and Amazon as occupants. Three more CyrusOne buildings are rising at Fairfield, where state records list a Meta subsidiary. Operators often market these campuses under Dallas-Fort Worth names, though they sit 100 km or more south of Dallas. Nexus Data Centers is building its Apex campus outside Hubbard on its own natural-gas generation. State records list Anthropic as its occupant.
A long pipeline of planned campuses follows. Cipher Digital plans a campus beside the Sandy Creek plant near Riesel. Galaxy Digital bought about 500 acres in McGregor. Infrakey DC Parks plans a park near Elm Mott, north of Waco. NRG Energy plans data centers beside a new gas plant on former mine land near Jewett. In Hill and Leon counties, RCM Hill, Provident, Belltown Power and Crusoe have proposed large campuses. On the RELLIS campus in Bryan, ThisWay Global is finishing an AI compute center it bought out of bankruptcy.
Advantages
-
Power plant sites. Large gas and coal plants dot the region, with transmission already built. Calpine's deals with CyrusOne show how a plant owner can sell land, power and grid access together.
-
Natural gas. Pipelines cross the region, so developers can build their own generation on site.
-
Location. The region sits in the Texas Triangle between Dallas-Fort Worth, Austin and Houston. I-35 and I-45 link it to all three metros.
-
Land. Ranchland, former mine land and industrial parks offer parcels of hundreds or thousands of acres.
-
Taxes. Texas levies no personal income tax. Qualifying data centers can claim a state sales tax exemption on equipment and electricity.
-
Talent. Baylor University, Texas State Technical College and Texas A&M University train engineers and technicians.
Challenges
-
Grid queue. By mid-2026 ERCOT tracked more than 400 GW of large-load requests, mostly from data centers. Its first batch of large-load connections awaits final classification in December 2026.
-
State permit freeze. In September 2026 Governor Greg Abbott told the Texas Commission on Environmental Quality (TCEQ) to hold data center air permits during a state audit. Governor-elect Gina Hinojosa has pledged to freeze new approvals until the Legislature acts in 2027.
-
Local opposition. Residents have packed hearings in Lacy Lakeview, McGregor, Hillsboro and Leon County over noise, traffic and water. In April 2026 Nexus withdrew a Hill County tax abatement request after residents objected.
-
Shifting county rules. Texas counties have no general zoning power. Hill County paused new data centers in May 2026, then rescinded the pause in June after a developer sued.
-
Water. Cooling water is a top local worry in a drought-prone state. Developers answer with closed-loop cooling and treated wastewater.
Trends
-
Campuses move to the power plant. CyrusOne's two Calpine campuses, Cipher's Sandy Creek site and NRG's Jewett project pair data halls with power plants. In May 2026 the Public Utility Commission of Texas (PUCT) approved the Freestone co-location, with conditions.
-
Hyperscalers arrive as tenants. State records name Google, Amazon, Meta and Anthropic as occupants of developer-built campuses in the region.
-
Developers bring their own power. Nexus, Infrakey and Belltown plan on-site gas generation beside or in place of grid power.
-
Crypto firms turn to AI. Cipher Mining renamed itself Cipher Digital in February 2026 as it moved from bitcoin mining to AI hosting. Galaxy Digital chose McGregor for its second Texas AI campus.
-
Nuclear on the horizon. In February 2025 the Texas A&M University System chose four developers to build small reactors at its RELLIS campus in Bryan.
Power and Policy
ERCOT runs the grid across the region, and the PUCT regulates it. Oncor delivers power in Waco, and Bryan Texas Utilities serves Bryan. Cooperatives such as Heart of Texas, HILCO and Navarro County Electric Cooperative serve rural areas. Brazos Electric Power Cooperative, based in Waco, sells wholesale power to member cooperatives. Senate Bill 6, signed in June 2025, makes new loads of 75 MW or more share their interconnection costs. It also requires those loads to accept curtailment during grid emergencies. The TCEQ issues air permits for on-site gas plants.