Overview
Lombardy holds most of Italy's data centre capacity, and most of that sits around Milan. Since 2024, large campus plans have spread from the Milan belt into the provinces of Bergamo, Brescia, Pavia, Lodi and Cremona. Grid requests and local protests have grown with them. In June 2026 Lombardy passed the country's first regional data-centre law.
History
Early sites outside central Milan served carriers and large companies. An internet data centre opened in a converted building at Cesano Maderno, in Brianza, in 2001. It now runs as part of Noovle, TIM's cloud unit. Eni opened its Green Data Center at Ferrera Erbognone, in Pavia province, in October 2013. It sits beside an Eni gas-fired power station and houses the group's supercomputers. Elmec opened its Tier IV certified BR4 data centre on a former foundry site at Brunello, in Varese province, in March 2016.
Investment picked up in 2025. In February Eni signed a letter of intent with MGX and G42 to build AI data centres in Italy, starting beside the Green Data Center. In May OVHcloud opened its first Italian data centre, in a former EDS facility at Inverno e Monteleone. In June Qarnot opened a pilot inside A2A's Lamarmora plant in Brescia, piping server heat into the city's district-heating network. In November A2A set aside €1.6 billion for data centres through 2035.
Deals and approvals followed in 2026. In May the government declared EdgeConneX's Italian campus programme, which includes a site in Lodi province, of strategic national interest. Scaleway bought Qarnot in July and took over the Brescia pilot. In August the European Commission cleared the joint venture between Eni and Khazna.
The Market Today
The Milan metro is the core of the market. It holds the campuses of Equinix, Data4 and STACK, the MIX internet exchange and the cloud regions of AWS, Google and Microsoft.
Bergamo province is the second cluster. Aruba's campus at Ponte San Pietro has run since 2017, and its fourth building is due in early 2028. Retelit runs smaller data centres in Bergamo and Brescia. Echelon plans a campus at Treviglio that reuses an existing industrial building.
In Brescia, A2A plans a data centre for AI and colocation inside its Lamarmora complex, with 2028 as its target. It will draw power from A2A's waste-to-energy plant and sit next to the district-heating network. Scaleway runs the former Qarnot pilot in the same complex.
Pavia province holds the region's energy-led builds. Eni and Khazna plan an AI campus beside the Green Data Center. STACK runs campuses at Siziano, on the Milan border, and at Vellezzo Bellini. Microsoft has been building a campus in the north of the province since January 2026.
Elsewhere, EdgeConneX has begun site works on a former refinery at Bertonico, in Lodi province. Green 1 has proposed a large campus at Pozzaglio ed Uniti, in Cremona province. In Monza and Brianza, Noovle runs the Cesano Maderno data centre, and QTS plans a three-building campus on a former IBM plant.
Advantages
-
Demand. Lombardy produces about 23% of Italy's GDP, the largest share of any region.
-
Power stations. Eni, A2A and EdgeConneX have placed campus plans beside large gas-fired plants at Ferrera Erbognone, Cassano d'Adda and Bertonico.
-
Industrial land. Former refineries, factories and foundries offer land zoned for industry. Lombardy's law cuts building levies by 10% to 30% on reused sites.
-
Heat reuse. A2A runs district-heating networks in Brescia and Milan. The Brescia pilot already feeds server heat into the city's network. A2A has also agreed with Equinix to recover heat from its Milan campus.
-
Low seismic hazard. Under the 2014 regional map, all but 57 Lombard comuni sit in Italy's two lowest seismic hazard zones.
Challenges
-
Grid queue. In November 2026 Terna reported 316 data-centre connection applications in Lombardy, totalling 48.6 GW. Only 9 GW had an accepted connection solution. In Bergamo province alone, 15 requests in 14 comuni seek about 2.8 GW.
-
Local opposition. Residents' committees fight new campuses across the region. In September 2026 East Gate withdrew its plan at Travagliato, near Brescia, after the town refused it. At Certosa di Pavia, a petition against GSM's campus drew over 1,300 signatures.
-
Farmland approvals. Many proposals outside Milan sit on farmland and need planning changes. In October 2026 Pozzaglio ed Uniti closed its preliminary procedure for Green 1's campus and left the permit to the environment ministry.
-
Generator emissions. The largest backup-generator fleets go to national environmental review. Ministry reviewers have asked Echelon's Treviglio project to study its generators' combined emissions.
Trends
-
Energy companies bring their own power. Eni's first phase will run on its existing combined-cycle plant. Eni also plans a new gas plant with carbon capture. A2A plans a campus at Cassano d'Adda, east of Milan, fed by its combined-cycle plant there.
-
The build is spreading beyond Milan. Campus plans now reach Bergamo, Brescia, Lodi, Pavia and Cremona provinces. A Bergamo member of parliament has asked the environment ministry to weigh the province's projects together, not town by town.
-
The state fast-tracks the largest projects. Five of Italy's seven programmes of strategic national interest sit in Lombardy. A government commissioner steers their permits.
Power and Policy
Terna runs the high-voltage grid and the connection queue. The Regulatory Authority for Energy, Networks and Environment (ARERA) sets connection rules and tariffs. The distributor e-distribuzione serves most of the region. A2A, formed in 2008 from the municipal utilities of Milan and Brescia, distributes power in both cities through Unareti. Since January 2025 its Duereti network has also served the belt east, south and west of Milan. Lombardy Regional Law 11 of 3 June 2026 set up a single regional permit window and raised building levies on farmland and parks. Resolutions of August 2026 split approvals between the Region and the environment ministry by generator size. Nationally, Decree-Law 21/2026, converted by Law 49/2026, created a single authorisation with a 10-month deadline.