Data Center Campus
Apple initially started with 160 acres in Prineville to build a 338,000 sqft data center. At the time the facility planned to draw 20 Megawatts
Apple acquired 200 additional acres for $3.6 million to support future expansion.
Apple started construction on its 2nd 338,000 sqft data center. (total of two buildings and 676,000 sqft)
Apple announced it would build a 3rd data center building of 270,000 sqft on the site.
| Site | Square Feet | Announced | Completed |
|---|---|---|---|
| Building 1 | 338,000 | 2012 | 2013 |
| Building 2 | 338,000 | 2015 | 2018 |
| Building 3 | 270,000 | 2016 | 2023 |
| Total | 946,000 |
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Hub TwoInterested in this information?Contact us | Apple |
Operational
|
░░░░ Request Dataset MW | 338,000 SqFt | 2013 |
| ProInterested in this information?Contact us | Apple |
Operational
|
░░░░ Request Dataset MW | 338,000 SqFt | 2018 |
| OneInterested in this information?Contact us | Apple |
Operational
|
░░░░ Request Dataset MW | 270,000 SqFt | 2023 |
In 2010, Apple reported that just 16% of its total facilities were powered by renewables. Within just six years, that number skyrocketed up to 96% in 2016. In 2018, Apple said that it has achieved 100% renewable energy. Source: cleantechnica.com.
As of early 2018, Apple had 25 operational renewable energy projects around the world, totaling 626 MW of generation capacity. Notably, 286 MW of solar PV generation came online in 2017. There are 15 more projects under construction that represent over 1.4 GW of renewable energy generation across 11 countries.
In Prineville, Ore., the Apple signed a 200 MW power purchase agreement for an Oregon wind farm, the Montague Wind Power Project, set to come online by the end of 2019.
Appleās data center in Maiden, N.C., is supported by projects that generate 244 million kWh of renewable energy per year, which is equivalent to the energy used by 17,906 North Carolina homes.