Data Center Campus

Apple: Prineville Campus

3 sites Bend Prineville
Operational
Fully operational facility
Operated by:

Campus at a Glance

3 data centers on this campus
First built in 2013
Total building size: 946,000 SqFt
Coordinates: 44.2889, -120.87016
░░░░ Request Dataset MW
Operational
░░░ Request Dataset MW
Under Construction
░░░ Request Dataset MW
Planned

Timeline

2012

Apple initially started with 160 acres in Prineville to build a 338,000 sqft data center. At the time the facility planned to draw 20 Megawatts

2015:

Apple acquired 200 additional acres for $3.6 million to support future expansion.
Apple started construction on its 2nd 338,000 sqft data center. (total of two buildings and 676,000 sqft)

2016:

Apple announced it would build a 3rd data center building of 270,000 sqft on the site.

Power:

  • Apple signed a deal to purchase 200 megawatts of power from the Montague Wind Power Project. The wind farm is located in Gilliam Country, Oregon.
  • Separately, Apple made a deal to buy 56 megawatts from Avangrid Renewables (Solar Star Oregon II) located near the Prineville campus.
  • The data center campus used 115,000-megawatt hours of electricity in 2016
Site Square Feet Announced Completed
Building 1 338,000 2012 2013
Building 2 338,000 2015 2018
Building 3 270,000 2016 2023
Total 946,000

Buildings

Sites on this Campus

Site Operator Status Operational Building Size Built
Hub TwoInterested in this information?Contact us Apple
Operational
░░░░ Request Dataset MW 338,000 SqFt 2013
ProInterested in this information?Contact us Apple
Operational
░░░░ Request Dataset MW 338,000 SqFt 2018
OneInterested in this information?Contact us Apple
Operational
░░░░ Request Dataset MW 270,000 SqFt 2023

Map and Nearby Locations

Apple: Prineville Campus Power Growth Over Time

+33% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Campus Photos

Operating Company

Operated by:

Apple's Move to Renewable Energy

In 2010, Apple reported that just 16% of its total facilities were powered by renewables. Within just six years, that number skyrocketed up to 96% in 2016. In 2018, Apple said that it has achieved 100% renewable energy. Source: cleantechnica.com.

As of early 2018, Apple had 25 operational renewable energy projects around the world, totaling 626 MW of generation capacity. Notably, 286 MW of solar PV generation came online in 2017. There are 15 more projects under construction that represent over 1.4 GW of renewable energy generation across 11 countries.

In Prineville, Ore., the Apple signed a 200 MW power purchase agreement for an Oregon wind farm, the Montague Wind Power Project, set to come online by the end of 2019.

Apple’s data center in Maiden, N.C., is supported by projects that generate 244 million kWh of renewable energy per year, which is equivalent to the energy used by 17,906 North Carolina homes.