Data Center News

Read Colorado Regulators Allege QTS Built Aurora Data Centers Without Air Permits
Colorado's Air Pollution Control Division (APCD) alleges [QTS Data Centers](https://baxtel.com/data-centers/qts-data-centers) built new data centers at its Aurora campus without the required state ...

Colorado Regulators Allege QTS Built Aurora Data Centers Without Air Permits

November 11, 2026 QTS Data Centers

Colorado's Air Pollution Control Division (APCD) alleges QTS Data Centers built new data centers at its Aurora campus without the required state air permits. The October notice of violation, reported by CPR News on Nov. 10, covers the two buildings QTS is adding at 1160 North Gun Club Road in...

Read more
Read Mubbadrah Consortium Plans $3B, 400MW AI Campus in Oman; Crusoe Eyes Offtake
A consortium led by Omani investment group Mubbadrah Investment plans an AI data center campus of up to 400 MW in Salalah, [Oman](https://baxtel.com/regions/oman), backed by $3 billion of initial i...

Mubbadrah Consortium Plans $3B, 400MW AI Campus in Oman; Crusoe Eyes Offtake

November 11, 2026 Crusoe

A consortium led by Omani investment group Mubbadrah Investment plans an AI data center campus of up to 400 MW in Salalah, Oman, backed by $3 billion of initial investment, DCD reported Wednesday. US AI infrastructure firm Crusoe has indicated interest in becoming an off-taker. The facility would...

Read more
Read 19000-200 Holdings Files $8B Data Center Plan For Quanah, Texas
An affiliate of [Integra](https://baxtel.com/data-centers/integra) has registered $8 billion of new construction a![constructionreviewonline.com](/rails/active_storage/representations/proxy/eyJfcmF...

19000-200 Holdings Files $8B Data Center Plan For Quanah, Texas

November 10, 2026 Integra

An affiliate of Integra has registered $8 billion of new construction at a data center campus in Quanah, Texas. The filing with the Texas Department of Licensing and Regulation covers Building 5, a 288,355-square-foot single-story data center at 4628 Four Corners Road in Hardeman County. The TDLR...

Read more
Read Integra Files $8B Building at 756MW Quanah Data Center Campus in Texas
Integra Mission Critical has registered an $8 billion data center building at its planned 756-megawatt campus near Quanah, in Hardeman County, Texas. The [Texas Department of Licensing and Regulati...

Integra Files $8B Building at 756MW Quanah Data Center Campus in Texas

November 09, 2026 Integra

Integra Mission Critical has registered an $8 billion data center building at its planned 756-megawatt campus near Quanah, in Hardeman County, Texas. The Texas Department of Licensing and Regulation filing, dated Oct. 27, sets construction from Nov. 1, 2026 to Dec. 31, 2028. It assigns no tenant....

Read more
Read Crusoe Signs 106MW Paraguay AI Cloud Partnership With Araico
[Crusoe](https://baxtel.com/data-centers/crusoe) signed a [strategic partnership](https://markets.businessinsider.com/news/stocks/crusoe-partners-with-araico-to-deploy-ai-cloud-infrastructure-in-pa...

Crusoe Signs 106MW Paraguay AI Cloud Partnership With Araico

October 23, 2026 Crusoe

Crusoe signed a strategic partnership with Araico, a Paraguayan energy and infrastructure developer, to build AI compute infrastructure powered by the Itaipú Hydroelectric Dam. The first deployment is planned for mid-2027, with a path to 106 MW of IT capacity. Under the partnership, Araico leads...

Read more
Read Crusoe Takes 40MW Second Phase At Polar's Hydro-Powered Norway Campus
[Crusoe](https://baxtel.com/data-centers/crusoe) will take a second, larger building at [Polar Data Centers](https://baxtel.com/data-centers/polar-dc)' Tørdal campus in Norway. Polar announced the ...

Crusoe Takes 40MW Second Phase At Polar's Hydro-Powered Norway Campus

October 22, 2026 Crusoe

Crusoe will take a second, larger building at Polar Data Centers' Tørdal campus in Norway. Polar announced the expansion on Oct. 21 (announcement). The new building, DRA02, will add 40MW of liquid-cooled critical IT capacity on hydroelectric power and is due online in late 2027. Crusoe plans...

Read more
Read IREN Proposes 900MW Redbank Campus Near Wagga Wagga, Power Not Yet Secured
IREN outlined early plans this week for Redbank, a proposed 900 MW data center campus near Wagga Wagga in regional [New South Wales](https://baxtel.com/regions/new-south-wales). The Nasdaq-listed o...

IREN Proposes 900MW Redbank Campus Near Wagga Wagga, Power Not Yet Secured

October 14, 2026 IREN

IREN outlined early plans this week for Redbank, a proposed 900 MW data center campus near Wagga Wagga in regional New South Wales. The Nasdaq-listed operator took the proposal to the local community ahead of a scoping report due to the state's Department of Planning, Housing and...

Read more
Read Crusoe Files For $4.8B Data Center Campus In Jayton, Texas
Crusoe has filed plans with the [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/tabs/search) for a two-building data center campus in Jayton, in rural Kent County, Texas, ...

Crusoe Files For $4.8B Data Center Campus In Jayton, Texas

October 02, 2026 Crusoe

Crusoe has filed plans with the Texas Department of Licensing and Regulation for a two-building data center campus in Jayton, in rural Kent County, Texas, carrying an estimated investment of $4.8 billion. The filings, first reported by Data Center Dynamics, place the site along County Road 233...

Read more
Read Crusoe Plans $4.8bn Data Center Campus in Jayton, Texas
Crusoe has filed plans for two data center buildings in Jayton, Texas.
According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Roa...

Crusoe Plans $4.8bn Data Center Campus in Jayton, Texas

October 02, 2026 Crusoe

Crusoe has filed plans for two data center buildings in Jayton, Texas. According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Road 233 and P2390 at an unspecified address in Jayton, Kent County. Each data center will span 759,260...

Read more
Read Crusoe Confirms Google AI Campus In Texas With 531MW Wind Link
Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company [said on Sept. 28](https://www.crusoe.ai/resources/newsroom/crusoe-developing-d...

Crusoe Confirms Google AI Campus In Texas With 531MW Wind Link

October 01, 2026 Crusoe

Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company said on Sept. 28. The site sits outside Amarillo, and it pairs with 531 megawatts of adjacent West Texas wind, a design that puts generation rather than land at the center of...

Read more
Read Crusoe Ends $1.25B Boom Supersonic Turbine Order for AI Data Centers
[Crusoe](https://baxtel.com/data-centers/crusoe) has dropped its $1.25 billion launch order for Boom Supersonic's Superpower gas turbines, ending a plan to power AI campuses with turbines derived f...

Crusoe Ends $1.25B Boom Supersonic Turbine Order for AI Data Centers

September 26, 2026 Crusoe

Crusoe has dropped its $1.25 billion launch order for Boom Supersonic's Superpower gas turbines, ending a plan to power AI campuses with turbines derived from the engine behind its Overture supersonic airliner. Boom founder and CEO Blake Scholl said on Friday that the two Denver companies are...

Read more
Read Crusoe Secures $3.9B For AI Data Center Expansion
AI data center and cloud company Crusoe has raised $3.9 billion in a Series F funding round, valuing the company at $30.9 billion. The round was co-led by Atreides Management, Mubadala Capital, and...

Crusoe Secures $3.9B For AI Data Center Expansion

September 18, 2026 Crusoe

AI data center and cloud company Crusoe has raised $3.9 billion in a Series F funding round, valuing the company at $30.9 billion. The round was co-led by Atreides Management, Mubadala Capital, and Valor Equity Partners, with additional investment from Founders Fund, GIC, Nvidia, QIA, Radical...

Read more
Read Crusoe Partners With Aalo on Nuclear-Powered AI Data Centre Project
Crusoe has partnered with SMR developer Aalo Atomics to deploy what the companies describe as the world's first nuclear-powered AI data centre. The partnership will see a Crusoe Spark modular data ...

Crusoe Partners With Aalo on Nuclear-Powered AI Data Centre Project

July 30, 2026 Crusoe

Crusoe has partnered with SMR developer Aalo Atomics to deploy what the companies describe as the world's first nuclear-powered AI data centre. The partnership will see a Crusoe Spark modular data centre deployed at Idaho National Laboratory in 2027, powered by Aalo’s 50MWe Pod reactor. The...

Read more
Read Crusoe Tied to Proposed Data Center Development in Virginia's Franklin County
A proposed data center project could be coming to Franklin County, Virginia. Local media report that county officials have been in discussions with Crusoe over the potential "Project Flash" develop...

Crusoe Tied to Proposed Data Center Development in Virginia's Franklin County

July 16, 2026 Crusoe

A proposed data center project could be coming to Franklin County, Virginia. Local media report that county officials have been in discussions with Crusoe over the potential "Project Flash" development since November. Few details have been disclosed, but the project is reportedly being...

Read more
Read Crusoe Temporarily Stops 1.8GW Data Center Build in Wyoming
Crusoe has paused development of Project Jade, a planned 1.8GW data center campus in Cheyenne, Wyoming that was announced last year and designed to potentially scale up to 10GW. The project was bei...

Crusoe Temporarily Stops 1.8GW Data Center Build in Wyoming

June 10, 2026 Crusoe

Crusoe has paused development of Project Jade, a planned 1.8GW data center campus in Cheyenne, Wyoming that was announced last year and designed to potentially scale up to 10GW. The project was being developed in partnership with Blackstone-backed energy company Tallgrass. Crusoe said it has...

Read more
Read Iren Powers up Initial Phase of Sweetwater Data Center Campus
Iren Powers up Initial Phase of Sweetwater Data Center Campus

Iren Powers up Initial Phase of Sweetwater Data Center Campus

May 06, 2026 IREN

Data center and cloud firm Iren has energized a new campus in Texas. The Nasdaq-listed company this week announced the successful energization of its 1.4GW Sweetwater 1 data center site in West Texas. The firm’s two Sweetwater campuses, both located outside Sweetwater in Fisher County, are...

Read more
Read Soluna Buys 150MW Wind Farm in West Texas for 300MW Data Center Project
Soluna Buys 150MW Wind Farm in West Texas for 300MW Data Center Project

Soluna Buys 150MW Wind Farm in West Texas for 300MW Data Center Project

April 07, 2026 Soluna

The company acquired the Briscoe Wind Farm for $53 million, which is located adjacent to its Project Dorothy sites, where it currently operates two data centers, Dorothy 1 and Dorothy 2. The third facility, Dorothy 3, is slated for development on a 300-acre land parcel located next to the other...

Read more
Read Crusoe Plans Modular Data Center Deployment at Energy Vault’s Snyder, Texas Technology Center
Crusoe Plans Modular Data Center Deployment at Energy Vault’s Snyder, Texas Technology Center

Crusoe Plans Modular Data Center Deployment at Energy Vault’s Snyder, Texas Technology Center

February 12, 2026 Crusoe

US energy storage firm Energy Vault has partnered with AI infrastructure provider Crusoe to deploy modular data centers at Energy Vault’s technology center in Snyder, Texas.“Crusoe is executing against a clear market imperative: customers need scalable compute delivered quickly and reliably,”...

Read more
Read QTS Drops Plan for Data Center near Madison, Wisconsin
QTS Drops Plan for Data Center near Madison, Wisconsin

QTS Drops Plan for Data Center near Madison, Wisconsin

January 30, 2026 QTS Data Centers

QTS has backed off plans to develop a data center near Madison, Wisconsin, after pushback from local officials. The company has dropped plans for a campus in the Village of DeForest after the village announced its intention to deny an annexation request related to the project.“After individual...

Read more
Read Crusoe to Deploy in Starcloud Satellite Data Center
Crusoe to Deploy in Starcloud Satellite Data Center

Crusoe to Deploy in Starcloud Satellite Data Center

October 22, 2025 Crusoe

Neocloud Crusoe is going to space and has revealed plans to deploy on a Starcloud satellite scheduled to launch in late 2026, and offer limited GPU capacity from space by early 2027. This comes ahead of the expected launch of the Starcloud-1 satellite this November. About the size of a small...

Read more
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.